StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Trust Grain Belt Express?

4/24/2015

2 Comments

 
Silly!  But that's exactly what Grain Belt Express expects the Missouri Public Service Commission to do -- issue a permit for the project and then trust Grain Belt Express to later meet all the requirements for a permit.  In the words of the attorney for one of the intervening landowner groups:
Even though the Commission gave GBE a second chance to provide the additional information the Commission said it requires in order to make a decision in this case, GBE did not provide the requested information. Much of the requested information—for example, the RTO interconnection studies—will not be available for some time, perhaps years. And, GBE may never be able to get the required consents from all of the county commissions. GBE’s general attitude is summed up thusly: Trust us—we will give you the information only after you give us our CCN.
As you may recall, instead of making a decision on the application of Grain Belt Express for a Certificate of Convenience and Necessity after going through all the motions of a contested case (discovery, testimony, evidentiary hearing), the MO PSC issued an Order demanding more information from the applicant.  This would be additional evidence submitted after the hearing record had closed.  This generates due process concerns, and the PSC had asked the parties how they wanted to deal with this submission of additional evidence.

The response of of Show Me Concerned Landowners points out that Clean Line didn't actually submit the information ordered -- in many instances, it submitted excuses for not providing information, claiming that it would provide the necessary information AFTER the MO PSC issued the CCN.  Clean Line seems to overlook the fact that much of this information is REQUIRED in order to issue the permit in the first place!  No information, no permit.  It's as simple as that.
The Commission should not allow GBE to play this “which comes first—the chicken or the egg” game. Show Me recommends that the Commission deny GBE’s Application without prejudice. GBE is free to refile its Application after it obtains all of the relevant information and documentation that the law and this Commission require.
The Missouri Landowners Alliance, another landowner group, took a different approach to this permitting circus:  Asking that the entire legal process be repeated in order to allow this new evidence to be examined and rebutted by the other parties.  That should only add... oh... another year or so to the permitting process?

But wait, Clean Line is whining about the amount of time this is taking!  It's already been more than a year! 
The Commission’s supplemental procedure should be scheduled with consideration given to the time that has already elapsed in this case. The Company filed its Application for a Certificate of Convenience and Necessity on March 26, 2014, over 12 months ago. Staff and other parties conducted extensive discovery regarding the Company’s Application, testimony, and schedules. The Commission held eight local public hearings, which occurred on August 12 and 14, and September 3 and 4. Three rounds of pre-filed testimony occurred, and the Commission conducted five days of evidentiary hearings (November 10, November 12-14, and November 21).
...and then the Commission ordered GBE to submit new evidence after the record had closed.  Return to "Go!"

United for Missouri, another citizens' group, thinks the whole idea of asking for more evidence after the record is closed isn't legal in the first place and the PSC should just deny GBE's application outright:
UFM recommends that the Commission reject the Grain Belt Express Response and deny Grain Belt Express’ application because the Commission misapplied its rules in its March 11 Order. The Commission’s order, therefore, was unlawful, arbitrary and capricious. Further, a review of the Grain Belt Express Response shows that there is very little additional relevant evidence to be adduced in additional proceedings. As a result, further proceedings would be inappropriate and a useless exercise. Finally, a review of the Grain Belt Express Response confirms UFM’s argument in its briefs previously filed in this case, that the proposed facilities are a private enterprise not devoted to the public convenience or necessity, and therefore are not qualified to receive a certificate of convenience and necessity.
And the Missouri Farm Bureau can't resist pointing out how futile this whole exercise has been:
Another initial point pertains to the information provided on the number of voluntary easements Grain Belt Express has obtained from landowners on the proposed route. According to Supplemental Exhibit 1 of Grain Belt Express’ Response, out of 724 tracts of land, Grain Belt Express has acquired only 45 easements voluntarily—about 6.2%. Grain Belt Express has been aggressively pursuing voluntary easements from landowners for a year. Given Grain Belt Express’ lack of success in convincing landowners that this is a good project for Missouri, granting Grain Belt Express the power of eminent domain would be inappropriate.
Really?  Would the MO PSC really grant eminent domain to a company that's going to need to use it on 93.8% of the properties?

Perhaps the MO PSC should have just denied the application in the first place, instead of opening this can of worms.  It's not too late!
2 Comments

Clean Line Pretends its "Code of Conduct" Offers Protection to Landowners

2/5/2015

1 Comment

 
If Clean Line's "Code of Conduct for Land Agents" was any more than window dressing, landowner reports of harassment by Clean Line land agents wouldn't keep happening.  It's nothing but a piece of paper Clean Line uses as a fig leaf to cover its transgressions.

Who enforces the "Code?"  Clean Line says it does.  How is this enforcement undertaken?  Nobody knows.  Despite continual public statements that Clean Line doesn't condone the kind of behavior that has been reported by landowners over and over again, there's never any obvious "enforcement," and the company's agents simply continue harassing landowners.
In a recent letter to the editor, Ms. Mary Adair Horsechief stated that “a representative of Plains & Eastern Clean Line recently dropped by” her home and he told her she “had no recourse but to let them take our land for their use.” Clean Line takes these assertions seriously and we do not condone or endorse statements like the one Ms. Horsechief claims was made on our behalf. Clean Line is committed to treating every landowner with consideration and respect. We require our representatives to follow a Code of Conduct that can be downloaded from our website. We strive to maintain long-lasting relationships with landowners by working in a respectful and collaborative manner. If you have information on interactions you have had with a Clean Line representative that goes against this code, we would like to know. Please contact us at 1-877-573-2851 or [email protected] and someone will respond to you in a timely fashion.
Read Mary Horsechief's entire Letter to the Editor here.

This isn't the first report of heavy-handed Clean Line land agent tactics, and I doubt it will be the last.  There's something wrong with the company doing Clean Line's land acquisitions.  They're not abiding by the Code of Conduct.  What's the punishment?  Judging from the continuation of this behavior... there is no punishment.

If you had contracted a company to do a job, given them a set of rules, and then the company systematically violated those rules and caused your company bad will in the community that could ultimately derail your entire project, would you fire them?  I would.

Instead, Clean Line keeps making excuses for this kind of behavior and pretending it's doing something about it.  Oh, poppycock, Mario!  Actions speak louder than words!

However, the "Land Agent Code of Conduct" is an old transmission owner trick that has been recycled again and again.  In fact, Clean Line's "code" was plagiarized nearly word for word from previous "Codes of Conduct" used by Allegheny Energy for its TrAIL and PATH projects.  In its original form on the TrAIL project, the "Code" was enforceable by the court.  The very idea that the company responsible for these transgressions would police itself is ludicrous!

In addition, Mario goes on and on disseminating his "facts" about how his project won't have health effects and will provide "opportunities" for landowners.  He's preaching to the choir.  No matter how many times Clean Line repeats this mantra, nobody believes it.  A company selling the benefits of its own project is ALWAYS suspected of dishonesty and bias from its public.  There is no amount of "information" from the company that's going to turn public opinion.  It's just not going to happen.

Here's what's actually happening... a fantastically researched and fairly presented story about Clean Line from NPR, Big Wind Blowing Through North Arkansas.  Give it a listen.

The jig is up, Clean Line!
1 Comment

"A Significant and Unwarranted Intrusion"

12/31/2014

1 Comment

 
Just one more post about Requests for Rehearing of the Illinois Commission's issuance of a conditional permit for the Rock Island Clean Line.

The Illinois Landowners Alliance not only reiterates the arguments put forth by ComEd and the Illinois Farm Bureau, but adds a stylish lambasting of the Commission for permitting "a significant and unwarranted intrusion upon landowners."
ILA’s witnesses and its many other members have expressed repeatedly their uniform opposition to the Project, routing and treatment of landowners and their concerns. The Order’s granting of a CPCN to Rock Island will permit Rock Island to force its way onto landowner property to “make land surveys and land use studies” (220 ILCS 5/8-510), a significant and unwarranted intrusion upon affected landowners for a project that is so speculative and tenuous.
Although the ICC significantly conditioned RICL's permit before any actual construction begins, and denied them eminent domain authority at this time, the ICC also allowed RICL immediate access to private property to conduct its "surveys."

It's a powder keg.  Let's hope it doesn't explode before the ICC reconsiders its misguided decision to order the trespassing and destruction of private property by a company with no financial assets.  The landowners don't seem to have changed their opinion about RICL and probably aren't going to welcome them to their properties with open arms and a forgiving attitude.  I hope the ICC thinks this though...
1 Comment

The Bluff and Bluster of Clean Line's Fantastical Business Plan

12/2/2014

3 Comments

 
Finally got around to reviewing the Illinois Commerce Commission's 200+ page final Order on Clean Line's RICL project.  Imagine my shock and horror to find that the actual Order bore no resemblance to the posturing Clean Line did for the media immediately following the Commission's vote.

Clean Line is nothing if not optimistic about its business plan to construct nearly 2000 miles of new "merchant" transmission lines across eight Midwestern states.  However, Clean Line's claims rarely comport with reality.  Isn't it odd that Clean Line had a press release ready to go the second the Commission voted?  It's all about pretending the Commission's decision "marks a critical milestone needed to deliver low-cost wind energy to Illinois and [those mysterious, unnamed] states farther east," no matter what the actual Order said.

And the press ate it up.  Shame on them!  The rest of us have been snickering at how much egg ended up on Clean Line's face for running with a media fantasy, and now the REAL story shall be told.

The ICC's Order issued a CPCN for the proposed business plan, finding it would be "needful and useful to promote competitive electricity markets in Illinois" if it ever gets built.  However, the Commission also found that RICL is not necessary to provide adequate service to customers, and that is is not necessary.  In addition, the Order requires Clean Line to jump some pretty high hurdles to make its business plan actually happen before it can build anything.
  A couple of conditions the ICC attached to the CPCN require that the company make a compliance filing demonstrating that it has funds available to construct the entire project before beginning any construction.  The ICC also attached a stipulation making the CPCN null and void if Clean Line attempts to allocate costs of its project to Illinois ratepayers through regional cost allocation administered by regional transmission organizations and FERC.  And, all this must happen within 2 years from the date of issue.  Tick-tock, Clean Line!

Oh... where to begin?  Let's talk about that financing stipulation.  In order to convince lenders to pony up the money to build the project, Clean Line must demonstrate an income stream.  It needs to have signed contracts with shippers or end users.  It has no end users.  The proposed shippers have not even been constructed yet.  In order to construct these mythical shippers (wind farms), the wind farms also have to borrow money to construct their projects.  In order to receive financing to build, these shippers must also demonstrate an income stream via signed contracts with purchasers.  It's a headache-inducing string of dominoes fraught with risk.  Utilities hate risk.  If utilities need to purchase renewables, there's plenty of EXISTING renewables available at concrete prices.  Since none of Clean Line's shippers exist, none of their proposed prices can be negotiated into signed contracts.  Remember... only two years to get this done!  And if you think it's going to happen, I'm a fairy princess.

Because the ICC did not find the project necessary under Sec. 8-503 of the PUA, Clean Line's CPCN only authorizes the company to build on voluntarily-negotiated easements.  The easements Clean Line has managed to sign with landowners are few and far between.  The rest of the landowners have rejected Clean Line's efforts and may continue to do so.  Clean Line was so certain that it would be granted eminent domain authority to take property that it has disrespected landowners with fantastical claims that bear no resemblance to reality
, along with underhanded tactics and empty promises.  You've got to get up pretty early in the morning to fool a farmer.  Nobody's buying it.  And since Clean Line has already ruined any possible cordial relationship with landowners, it is unlikely to regain what has already been tossed away.

And that brings us to the match tossed into the powder keg...  the CPCN issued by the ICC:


The Commission also observes that the approval of a line route as part of this Certificate Order should facilitate negotiations with landowners, and that the issuance of the Certificate will enable Rock Island to gain access to the property to conduct surveys and related activities, which are steps characterized by Rock Island as important ones in which to engage in the near future.
That's funny.  The Commission was so uncertain about this company's financial resources that it required it to have financing in place before beginning construction, but yet this same company can now enter upon and damage private property to conduct its surveys, without the demonstrated financial resources to guarantee that landowners will be compensated for damages.  What happens when Clean Line's surveys damage private property and the company refuses to make landowners whole?  Where's the remedy for landowners?  Will the ICC be policing Clean Line's survey activities?  Will landowners be left swinging in the wind with only a civil remedy?  And, I don't think Clean Line barging onto private property and leaving a mess behind will "facilitate negotiations with landowners."  Call me jaded...

So, Illinois landowner groups now have been handed the task of figuring out how to protect their interests all on their own.  And they will.

Two years, remember that.

And, in addition, RICL has just barely begun the permitting process in Iowa, where thousands of landowners have joined forces as the Preservation of Rural Iowa Alliance, and hired counsel and witnesses to participate in the Iowa Utility Board's review of RICL.

Two years.

I'm thinking that this thing is NEVER going to happen.  The ICC Order requires Clean Line to perform in accordance with its fantastical business plan to get all this accomplished in two years.

So, despite sweeping bluster like
“The ICC approval is a great step forward for the Rock Island Clean Line project and brings Illinois one step closer to creating a cleaner energy future,” said Michael Skelly, President of Clean Line Energy. “We are grateful to the Commission for their careful consideration of our application and proposed route. By approving game-changing projects like the Rock Island Clean Line, Illinois will benefit from access to low-cost clean energy and job creation in the construction and manufacturing sectors.”
the Order doesn't actually move RICL closer to reality.  It simply starts the clock.  Tick-tock.

Todd Maisch, President of the Illinois Chamber of Commerce should be eating the words Clean Line put in his mouth:

Companies like Clean Line that propose electric transmission projects are forced to meet a high threshold to prove that their energy project serves the public need and benefits consumers.
...because Clean Line didn't actually meet the ICC's high threshold to be found necessary, and therefore has to make its plan a reality before it could be granted the authority to build the project and take land from unwilling owners.

Michael Cornicelli, Executive Vice President of the Building Owners and Managers Association of Chicago, or BOMA/Chicago also had some inapt words:
This project should demonstrate that independent, investor-driven transmission infrastructure can become a viable business solution in a traditionally utility-driven arena.
...but only if it can make its fantastical business plan into reality.   I think the ICC's Order demonstrates that merchant transmission projects undertaken outside the traditional regional planning process cannot succeed, but time will tell.  Two years.

Clean Line also makes fantasy claims about its ability to reduce carbon emissions:
The wind energy delivered by the Rock Island Clean Line will allow other generators to run less and burn less fuel by eliminating the need for the equivalent amount of energy to come from fossil fuels, thereby reducing pollution. More than 1.4 million homes will be powered by the renewable energy generated as a result of this project.
Because it is an intermittent resource, baseload fossil fuel generators will be required to run constantly to back up Clean Line.  The ramping up and down of baseload plants actually produces MORE emissions than running at a constant rate.  Clean Line's insistence that its transmission line will reduce fossil fuel generation on a basis equal to its production is unrealistic fantasy. 

And, we'll end with this:

Developing a project of this scale is a long-term undertaking...
Yes, indeed.  Two years.  Tick-tock!
3 Comments

Landowners Prevail Over Rock Island Clean Line Eminent Domain Scheme

11/26/2014

0 Comments

 
You won't be seeing variations of the word "approve" in my headline.  That's because the Illinois Commerce Commission decision yesterday was not a pivotal moment that sealed the project's success.

Far from it.

Although the actual Order has been withheld from the parties and the general public for the time being, I've been able to piece together a general idea of its contents from various news stories, along with knowledge of what was in the proposed order issued by ALJ Larry Jones several months ago.

Clean Line applied to the ICC under two separate statutes.
Rock Island therein requests an order granting it a certificate of public convenience and necessity (“CPCN” or “Certificate”), pursuant to Section 8-406 of the Act, authorizing it to operate as a transmission public utility in the State of Illinois and to construct, operate and maintain an electric transmission line (“Project”); and authorizing and directing it, pursuant to Section 8-503 of the Act, to construct the proposed line. 
News reports say that the Commission granted the CPCN under Section 8-406, but did NOT order it to construct the line under Section 8-503.

Sec. 8-406 makes it technically possible to construct the line, if it can acquire VOLUNTARY easements from all affected landowners. 

Only under Sec. 8-503 may the company be granted the authority to take property through eminent domain condemnation.  An order under 8-503 would set the company up to effect takings through mere procedural steps.  But the ICC DENIED Clean Line's application under Section 8-503.  Therefore, Clean Line would have to come back before the Illinois Commerce Commission with a second application for an order under Sec. 8-503 at some point in the future, with likely similar results.

ROCK ISLAND CLEAN LINE HAS BEEN DENIED EMINENT DOMAIN AUTHORITY TO TAKE PROPERTY IN ILLINOIS!

Big win for landowners!


Know this -- the ICC would never grant Clean Line eminent domain authority to take the majority of its route.  Usually, holdouts in transmission line cases that actually end up being taken via eminent domain are few and far between.  There's strength in numbers.

Feel free to say "no."  Isn't it ironic that a company that has been telling regulators and the media how well it has been "collaborating with landowners" would now actually have to... well... collaborate with landowners?  Perfect!  However, Clean Line's lies and underhanded tactics have inspired massive distrust by landowners.  And every farmer knows... you reap what you sow.
0 Comments

DOE's Section 1222 - More Questions Than Answers

10/17/2014

0 Comments

 
I got an email yesterday from DOE's Office of Electricity Delivery and Energy Reliability (OE) with a link to DOE's new Section 1222 FAQ.  FAQ stands for "frequently asked questions."  This is supposed to be a list of the questions about Section 1222 that you all have sent to Energy Secretary Ernest Moniz lately.  Instead of actually answering your specific questions though, Ernie's staffers first sent out a form letter response.

The form letter encourages the hoi polloi and affected landowners to make comment on the Environmental Impact Statement (EIS).  It insinuates that the public's only avenue for participation in a process that could ultimately condemn and take their property via eminent domain is through the EIS.  This is preposterous. 

The EIS simply decides where to put the transmission line to cause the least environmental damage.  It does not prevent environmental (or historic, cultural, and socioeconomic) damage.  Damage is allowed, as long as the company perpetrating it makes payment for "mitigation."  In other words your land and environment is for sale to the highest bidder.  Confining your comments to the EIS is a losing, feel-good way to contain you and stop you from causing a ruckus until after the decision is made.
  By that time, it will be too late.

During any state jurisdictional transmission permitting process, affected landowners may intervene and participate in the hearing process, providing evidence and pleading their case to the Public Service Commission who will ultimately make the decision on permitting and siting.  The DOE's Section 1222 "program" doesn't provide you landowner stakeholders with any due process to participate in the decision making.

Instead, companies standing to profit from Sec. 1222 were having their own little private party with DOE, urging DOE to hurry up and sign up to be Clean Line's land agent.

Due process?  No.  Landowners were being excluded.  So, the landowners crashed the party.  And the best DOE could offer them is this unhelpful FAQ?

A couple of affected landowners who looked at the FAQ last night has more questions than answers.  Everything from "what is OE?" to "what ever happened to Clean Line's Grain Belt Express Sec. 1222 application?"

What are the statutory requirements for a project under Sec. 1222?  DOE skips over this while patting you on the head and telling you not to worry about all that complicated stuff:
The DOE will conduct a thorough review that includes making all required statutory findings as well as consideration of the proposed project’s environmental impacts, the project’s technical and economic feasibility, and whether the project is in the public interest.
What are the decisional guidelines?  Or is DOE just making this crap up as they go?

What is "other due diligence?"
DOE will decide whether to participate in the proposed project, a decision which would include route selection, once all environmental reviews and other due diligence have been completed. The earliest a decision could be made is at least 30 days after issuing the Final EIS, which is not expected before 2015.
How can you participate in the decision making process outside the EIS?  How should landowner stakeholders be consulted in this process?  Where's the due process?
Issues Not Addressed in the EIS: Before DOE conducts its review of all of the factors discussed above, the applicant will be required to submit further information and update its original application. Once DOE receives the updated information, and deems the application complete, it will provide notice that the application is available for public review through a notice in the Federal Register and an announcement on the OE website. Publication of this notice in the Federal Register will begin a 45-day public comment period. The notice will describe how to comment on the application for the proposed project. All comments submitted during the comment period will be considered in the DOE’s ultimate decision as to whether to participate in the proposed project under the Section 1222 program.
Oh, now I know they're just making the rules up at they go.  Updated application?  Why?  So that Clean Line can address any shortcomings and make its application a little more legally bulletproof?  A "do-over," as we used to call it on the playground.  Where is this 45-day comment period written into the statute (hint:  it's not -- they just made it up!)

So, what to do?  Keep asking questions!  Submit your additional questions here and encourage Angela to flesh out her confusing FAQ.  And be sure to ask her... "Where's the due process for affected landowners?"
0 Comments

ICC Judge Issues PROPOSED Order on Rock Island Clean Line

8/20/2014

7 Comments

 
Last Monday, Illinois Commerce Commission ALJ Larry Jones issued his proposal for an Order of the Commission regarding RICL's request for authority to build its project in Illinois.  Note that this is just a proposal, it is NOT an official Order of the Commission and has no authority unless adopted by the five member Commission.

Meanwhile, the legal debate will continue.  Under Section 200.830 of the Rules, exceptions to the Proposed Order and replies thereto may be filed by the parties.

Let's just start out by stating that the Proposed Order (P.O., for short) is a beast -- 216 pages of repetitive back and forth, and lots of legal prose.  If you've actually read the whole thing, congratulations!  It took me most of the week to plow through it and to do the research to answer my own questions about certain parts.

First of all, we need to know what RICL asked the ICC to do.
In this proceeding, Rock Island Clean Line LLC (“Rock Island,” “RICL” or “RI”) filed the above-referenced petition with the Illinois Commerce Commission (“Commission” or “ICC”) pursuant to Sections 8-406 and 8-503 of the Public Utilities Act (“Act”),  220 ILCS 5/1-101, et seq.

Rock Island therein requests an order granting it a certificate of public convenience and necessity (“CPCN” or “Certificate”), pursuant to Section 8-406 of the Act, authorizing it to operate as a transmission public utility in the State of Illinois and to construct, operate and maintain an electric transmission line (“Project”); and authorizing and directing it, pursuant to Section 8-503 of the Act, to construct the proposed line. 
Section 8-406 governs the following:
Whenever after a hearing the Commission determines that any new construction or the transaction of any business by a public utility will promote the public convenience and is necessary thereto, it shall have the power to issue certificates of public convenience and necessity. The Commission shall determine that proposed construction will promote the public convenience and necessity only if the utility demonstrates: (1) that the proposed construction is necessary to provide adequate, reliable, and efficient service to its customers and is the least‑cost means of satisfying the service needs of its customers or that the proposed construction will promote the development of an effectively competitive electricity market that operates efficiently, is equitable to all customers, and is the least cost means of satisfying those objectives; (2) that the utility is capable of efficiently managing and supervising the construction process and has taken sufficient action to ensure adequate and efficient construction and supervision thereof; and (3) that the utility is capable of financing the proposed construction without significant adverse financial consequences for the utility or its customers.
Here's what the P.O. determined about RICL's request under 8-406:
Having reviewed the record, the Commission finds, with regard to the first alternative showing in Section 8-406(b)(1), that Rock Island has not demonstrated that the Project is necessary to provide adequate, reliable, and efficient service to customers within the meaning of Section 8-406(b)(1).

BUT, regarding the second alternative:


In conclusion, upon consideration of the record and the determinations contained above, and subject to the conditions set forth above and elsewhere in this Order, the Commission finds that the Project will provide an opportunity for the delivery of more renewable energy into Illinois, and will promote the development of an effectively competitive electricity market that operates efficiently, including with respect to renewable energy; is equitable to all customers; and is the least cost means of satisfying those objectives, within the meaning of Section 8-406(b)(2).
The "conditions" attached to the judge's proposed conclusion are as follows:
Prior to recovering any Project costs from Illinois retail ratepayers through PJM or MISO regional cost allocation, Rock Island will obtain the permission of the Illinois Commerce Commission in a new proceeding initiated by Rock Island. For the purposes of the prior sentence, any system upgrades set forth in an interconnection agreement with PJM or MISO and the costs of which are allocated to Rock Island will be considered “Project costs.” For the avoidance of doubt, the phrase “recovering any Project costs from Illinois retail ratepayers through PJM or MISO regional cost allocation” includes the recovery of costs though PJM and MISO transmission service charges that are paid by retail electric suppliers in respect of their electric load served in Illinois.  

AND

As a condition of this Order, Rock Island shall not attempt to effect the interconnection until it has fully complied with the applicable requirements of PJM and the other conditions in this Order, and has signed all interconnection agreements.

AND (This is a biggie!)

Rock Island will not install transmission facilities for the Rock Island Clean Line Project on easement property until such time as Rock Island has obtained commitments for funds in a total amount equal to or greater than the total project cost.  For the purposes of this condition:

 (i) “install transmission facilities” shall mean to affix permanently to the ground transmission towers or other transmission equipment, including installation of bases and footings for transmission towers, but shall not include (A) preparatory work such as surveys, soil borings, engineering and design, obtaining permits and other approvals from governmental bodies, acquisition of options and easements for right-of-way, and ordering of equipment and materials, and (B) site preparation work and procurement and installation of equipment and facilities on property owned in fee by Rock Island including the converter station sites;

(ii) “easement property” shall mean property on which Rock Island has acquired an easement to install transmission facilities;

(iii)  “has obtained commitments for funds” shall mean (A) for loans and other debt commitments, that Rock Island has entered into a loan agreement(s) with a lender(s) and has received the loan funds or has the right to draw down the loan funds on a schedule that is consistent with the need for funds to complete the Project, and (B) for equity, that Rock Island or its parent company has received the funds from the equity investors or that the equity investors have entered into a commitment to provide funds on a schedule that is consistent with the need for funds to complete the Project; and  

(iv) “total project cost” shall mean the total estimated remaining cost, at the time that Rock Island is prepared to begin to install transmission facilities, for the following Project activities: engineering, manufacturing and installation of converter stations; transmission line engineering; transmission towers; conductor; construction labor necessary to complete the Project; right of way acquisition costs; and other costs necessary to complete the Project.  For reference, the total estimated project cost as of November 1, 2012 is $2.0 billion.

To allow the Commission to verify its compliance with this condition, Rock Island shall submit the following documents to the Director of the Financial Analysis Division and the Director of the Public Safety & Reliability Division at such time as Rock Island is prepared to begin to install transmission facilities:

a) On a confidential basis, equity and loan or other debt financing agreements and commitments entered into or obtained by Rock Island or its parent company for the purpose of funding the Rock Island Clean Line Project that, in the aggregate, provide commitments for funds for the total project cost;

b) An attestation certified by an officer of Rock Island that Rock Island has not, prior to the date of the attestation, installed transmission facilities on easement property; or a notification that such installation is scheduled to begin on a specified date;

c) A statement of the total project cost, broken out by the components listed in the definition of “total project cost,” above, and certified by an officer of Rock Island, along with a reconciliation of the total project cost in the statement to the total project cost as of November 1, 2012 of $2.0 billion; and

d) A reconciliation statement, certified by an officer of Rock Island, showing that the agreements and commitments for funds provided in (a) are equal to or greater than the total project cost provided in (c).

So, the P.O. did not find that RICL was necessary, but did find that it would promote the development of a competitive electricity market (not that the current market doesn't already do that).  Therefore, the P.O. recommends that RICL be granted a Certificate of Public Convenience and Necessity under Section 8-406 because it satisfied the second part of (1) after the "or" (see 8-406 language above).  However, the proposed finding comes with HEFTY conditions and would expire two years after being granted.  Do you think RICL can get its stuff together to satisfy all the conditions AND get a permit from Iowa within two years?  Tick tock!  How many years has RICL been trying to make these projects work now?  Has it been 5 years already?

Now let's move on to RICL's request that the ICC "authorize" or direct it to construct the line under Section 8-503.  Remember that RICL told the ICC that they might not even construct the project after all if it wasn't profitable enough? 
The Commission has reviewed the evidence and arguments.  First of all, to the extent Rock Island is asserting that the criteria in Sections 8-406(b) and 8-503 are identical, and that a finding the Section 8-406(b) criteria have been met would automatically mean the Commission is required to grant the relief sought under Section 8-503, the Commission disagrees.  Such an interpretation would render Section 8-503 superfluous.    

ComEd and Staff argue that Rock Island’s request for Section 8-503 relief is premature, in that Rock Island is seeking authority that cannot be utilized given the contingencies, conditions and regulatory approvals still needed.    While the Commission is by no means suggesting that RI would have to satisfy every condition, contingency or uncertainty before Section 8-503 authorization may be granted, the Commission does agree with Staff and ComEd that under the circumstances, it would be premature to grant Section 8-503 relief to Rock Island in this proceeding.  

Rock Island claims Section 8-503 approval is needed now because it is one of the major regulatory approvals needed to satisfy potential lenders and investors; however, Rock Island does not explain how a Section 8-503 authorization is somehow more urgent or important in that regard than is the proceeding in Iowa, where the Project originates and the first 379 miles of the 500-mile line would be built.  Even Rock Island does not estimate a decision being reached in Iowa until 2015, assuming the formal proceeding has even begun there.

IT IS FURTHER ORDERED that the request for relief pursuant to Section 8-503 of the Act is not granted at this time; this determination is without prejudice to the filing of a request for such relief in the future. 
Authority under Section 8-503 is necessary to apply for eminent domain under Section 8-509, which reads:
When necessary for the construction of any alterations, additions, extensions or improvements ordered or authorized under Section 8‑503 or 12‑218 of this Act, any public utility may enter upon, take or damage private property in the manner provided for by the law of eminent domain.
But, the P.O. is NOT proposing that RICL be granted eminent domain authority at this time.  RICL may re-apply for Section 8-503 at a later date.  Important:  RICL does NOT have eminent domain authority to condemn and take property in Illinois at this time, and this proposed order would not give it to them!

But, the P.O. also proposed that the recommended CPCN issued under Section 8-406 would allow Section 8-510 of the Code, which states:
Land surveys. For the purpose of making land surveys, any public utility that has been granted a certificate of public convenience and necessity by, or received an order under Section 8‑503 of this Act from, the Commission may, 30 days after providing written notice to the owner thereof by registered mail, enter upon the property of any owner who has refused permission for entrance upon that property, but subject to responsibility for all damages which may be inflicted thereby.
The P.O. recommended granting RICL the Certificate required to enter onto private property under Section 8-510, and reasoned:
...the issuance of the Certificate will enable Rock Island to gain access to the property to conduct surveys and related activities, which are steps characterized by Rock Island as important ones in which to engage in the near future.
The P.O. proposes that RICL be granted authority to trespass upon, enter, and damage private property, although prohibited from taking that same property by eminent domain. Yet, it's clear that RICL at this time does NOT have any dedicated funds, so how would landowners be compensated for damages incurred in the surveying process? What protections are in place for landowners in the likely event that funds are not acquired to build the project and the company goes bankrupt?  At this time... none!

But, remember, this is only a PROPOSED Order, subject to more legal filings and alternative proposed language.  What the Commission actually approves may be radically different.

Meanwhile, keep up to date on all the RICL news and action alerts by liking BlockRICL on facebook or visiting their website.
7 Comments

Grain Belt Express Clean Line is a Threat to our Independence and Freedom

7/4/2014

1 Comment

 
Tammy Hammond is the founder of Rosewood Services, a facility that fosters an environment of independence, inclusion and productivity for individuals with developmental disabilities through education, work, recreation, and housing designed for their unique abilities.  On this Independence Day she shares her thoughts about the nature of sacrifice and the devastation the proposed Grain Belt Express Clean Line will have on her life, her programs, and most importantly, the independence of the clients she serves in Kansas. 

Grain Belt Express is a massive high voltage electric transmission line proposed to transport energy generated in the southwestern Kansas region to expensive east coast cities.  Purposed to provide attractive returns to foreign investors, Grain Belt Express is designed to increase America’s dependence on centralized electric generation and old fashioned overhead transmission that disturbs our rural communities and way of life.  Only through development of their own sources of renewable electricity will eastern states realize their own true independence, while keeping their energy dollars at home in their own communities.

Read Tammy's declaration of independence from Grain Belt Express, entitled "This Land is Our Land."  Here's a preview to get you started:
My name is Tammy Hammond, Kansas land owner for 30 years. As I sit here on
Independence Day 2014 my thoughts are consumed with the efforts of Grain Belt Express Clean Line's plan to run High Voltage Transmission Lines across my properties.
I'm very much opposed to the Grain Belt
Express 140 feet tall transmission towers,
carrying 750,000 volts of electricity, running
across our land. I could list pages of serious
health risks to my children and grandchildren, or provide statistics to the devastating de-valuation of property these High Voltage Power Lines will cause.
Probably, you have already heard those
arguments, so I would like to explain
something which I believe to be much more
profound...
I've been struggling for days with how to tell this story; how do I express with words why a
landowner will fight till their last breath, and their last dollar, to keep what is rightfully theirs?
How do you explain this so people understand the deep-rooted patronage of owning your
piece of the American dream...your Freedom in the heartland...the place you proudly call
home... What I discovered is something much deeper, much larger than Grain Belt Express....
I believe it is "American Spirit", how fitting to tell the story on July 4th, our Country's
Independence Day.

Click here to continue reading
Tammy's inspirational treatise ends with this message to the Sam Brownback political machine that stole the independence and freedom of hard working Kansas voters by greasing the approval of Grain Belt Express at his Kansas Corporation Commission:
So Today... this Message is for you, Grain Belt Express, Elected Officials or whoever is listening...
Do not underestimate our deep rooted sense of Freedom....
This is our land, my children's land, and so on for generations to come...
Earned with "our" blood, sweat and tears, it is
"we" who have the right to call this land home....
Make no mistake. We planted our "Flag of Freedom" and we will fight to
keep it...
you cannot have it...
you have not earned it...
we are here to stay...
1 Comment

Beware the Hurtado! and Other "Clean" Fairy Tales

6/8/2014

5 Comments

 
Our friends at Clean Line have been as busy as a nasty nest of yellow jackets this past week, while I was tied up with other things.  So, on this beautiful Sunday, let's hunker down around the campfire and catch up on some scary stories...

My multilingual, Arkansan friend, Doc, alerted me to an interesting discovery this week.  Clean Line's project manager for its Plains & Eastern "Clean" Line, slated to plow through Arkansas like Godzilla on his way to Tokyo, is a Mr. Mario Hurtado.  In the Spanish language, the word "hurtado" means "to steal."  So, Clean Line is sending out some guy named "to steal" to... ummm... steal land from Arkansans.  Brilliant!  Perhaps Clean Line watches too many old movies and expected its opponents in Arkansas to behave like movie characters...
...and not like multilingual PhD's.

So... Arkansas... Beware the Hurtado!

My friend Doc says he looks like this:
Meanwhile, in other "Clean" news from Arkansas...
"Clean" Line has submitted a second application for negotiated rate authority from the Federal Energy Regulatory Commission.

I guess their first one wasn't good enough, since they didn't even bother to mention it in their new filing.  So, inquiring minds want to know... is "Clean" Line just stupid, or are they trying to pull something on FERC?

Negotiated rate authority is no big thing, though.  It simply bangs out a plan for the company to negotiate rates with potential customers in a fair and non-discriminatory fashion.  It doesn't get them any customers.  It is not an "approval" of the project.  FERC's only authority over this project is ensuring its rate structure is fair.  FERC has no authority over the siting and permitting of this project.  Big deal, Mr. To Steal.

And, news from Missouri...

"Clean" Line has been quoting industry-influenced WHO studies as "proof" that their transmission projects will have no health effects on nearby residents.  However, a well-respected, local physician has been compiling and reviewing medical research on the health risks of the proposed "Clean" Line.  The Moberly Monitor did an indepth report about what Dr. Smith has found.  Shocking and dangerous!  Dr. Smith's findings are a MUST READ for every person in proximity to one of these "Clean" Lines.

Other news outlets have also picked up on Dr. Smith's EMF research, and the truth is spreading like wildfire!  SeeABC News, the News Democrat, and about 18 other major news outlets.

"Clean" Line needs to finish watching the movie that they've been using as the basis for their arrogant expectations of the intelligence and cunning of their local opposition.  They must not have watched far enough to see this scene yet:
5 Comments

CFRA Does Not Represent the People

6/3/2014

0 Comments

 
The Center for Rural Affairs has pissed off a whole new bunch of people, this time in Wisconsin, by sending out a "red alert" telling them this is their "last chance" to comment on the Badger-Coulee transmission project.  Of course it's not their "last chance"!

Carol Overland, who has been fighting the legal fight against unneeded transmission for many years, tells CFRA what the people REALLY think:
I'm disturbed to see that you're regarding Lu Nelsen and Center for Rural Affairs as a primary source.  Center for Rural Affairs is not an intervenor in this project.  Center for Rural Affairs is a paid transmission advocate, through the RE-AMP program, it is paid to to promote transmission.

A CfRA Director also sits on the RE-AMP Steering Committee.   It's unfortunate that these facts are not included in your article -- this interest should be disclosed, because they are neither objective nor representing public interests or farmer interests.  If their paid advocacy was not disclosed to you, that's an even more significant problem.
Read more about transmission toadie CFRA here, and check out the organization's source of funding.  It is receiving grants from entities I like to call "the environmental 1%" -- super rich, super clueless, city folk whose environmental tyranny is not a compliment to rural interests.

CFRA does not represent the people, although they are being paid well to pretend that they do.  Tell them they don't represent you!
0 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.